Job of the Month – October 2016

2016-10-26-ralph-099Description of Work: Removed and saved existing copper gutters to access fascia board and reinstall using new hidden hangers and adding new expansion joints as required, installed new metal slip flashing at existing eave metal, replaced fascia with AZEK, installed additional wood blocking in all soffits and installed new Vinyl InvisiVent soffit, installed new blocking at house wall and new AZEK crown molding, removed existing ridge vent and installed a new attic fan, installed new Hardie Board & Batten siding on rear gable and installed new AZEK rake trim.

Project Manager: Ralph Kuehne

Crew: Galen Desch, Gary Gamber, Michael Giordano, Buddy Adkins, Ryan Donet, Mike Kelly, Mark Fick

Estimator: Walt Willson